A water treatment plant expansion can involve much more than adding process capacity at an existing facility. Santa Monica’s Olympic Well Field Restoration and Arcadia Water Treatment Plant Expansion Project brings together groundwater wells, a dedicated transmission pipeline and new treatment processes to increase the city’s use of local water resources. The project’s design offers a useful example of how utilities can plan connected supply and treatment infrastructure while addressing construction and environmental considerations.
Why expand local water treatment capacity?
The project was developed to support the City of Santa Monica’s goal of increasing local water supplies and reducing reliance on imported water purchased from the Metropolitan Water District of Southern California. Its approach combines restoration of pumping capacity in the Olympic Well Field with expanded groundwater production and additional treatment capacity at the Arcadia Water Treatment Plant (WTP).
That system-level approach matters for infrastructure planning: producing more groundwater is only one part of the task. The water must also be conveyed to a treatment facility and processed to meet the project’s treatment objectives. The project therefore links well-field work to pipeline construction and upgrades at the receiving plant.
Three connected components
Olympic Well Field restoration
The well-field component includes two new domestic groundwater production wells, SM-8 and SM-9, and two injection wells, SM-10i and SM-11i. Lateral pipeline connections would link the production wells to the proposed Olympic Pipeline and connect the injection wells to recycled water pipelines. A further recycled water pipeline would connect SM-11i to a planned pipeline at the Santa Monica City Yards.
These elements serve distinct roles within the overall project. Production wells provide the groundwater intended for treatment, while the injection wells connect to recycled water infrastructure. Coordinating well construction with pipeline connections is essential to making the field part of a broader supply system rather than a collection of separate assets.
A dedicated groundwater pipeline
The proposed Olympic Pipeline is a new 16-inch water transmission pipeline. It would carry water extracted from the Olympic Well Field in Santa Monica to the new Olympic Advanced Water Treatment Facility (AWTF), which would be located at the Arcadia WTP in the City of Los Angeles.
The route crosses jurisdictional boundaries, making coordination among project components and agencies an important part of delivery. The project’s environmental review also identifies the pipeline alignment as an area requiring attention during construction, including measures for potential archaeological discoveries and hazardous materials where ground disturbance occurs.
New treatment processes at Arcadia
The Olympic AWTF would add treatment equipment designed to address key contaminants in Olympic Well Field groundwater. At the same location, the Arcadia WTP would be expanded to handle the additional flow. The project also includes reverse osmosis (RO) concentrate treatment technology intended to improve production efficiency, produce additional potable water and reduce concentrate discharges to the sewer system.
These are related but separate functions: the AWTF is designed to treat the incoming groundwater, while the Arcadia expansion provides capacity for the additional flow and incorporates concentrate treatment. The project describes an increase in overall raw-water treatment capacity from approximately 10 million gallons per day (mgd) to approximately 13 mgd. The document also gives annual capacity equivalents of about 11,300 and 14,700 acre-feet per year, respectively.
Environmental safeguards are part of project delivery
The project’s California Environmental Quality Act review identified potential impacts that would require mitigation during construction. These included air quality, biological and cultural resources, geology and soils, hazardous materials, noise and transportation. The review concluded that the identified potentially significant impacts could be reduced to less-than-significant levels through specified mitigation measures.
For construction teams and project managers, the measures illustrate the importance of embedding environmental requirements in planning and contractor documents. Examples include:
- Air quality: Requirements for diesel construction equipment and dust suppression at the Arcadia WTP.
- Biological resources: Nesting bird surveys or scheduling measures where construction may affect potential nesting areas.
- Cultural and paleontological resources: Worker awareness training, monitoring in specified circumstances and procedures to pause work if resources are discovered.
- Hazardous materials: Contingency planning for potentially contaminated soil or groundwater, plus surveys of structures and materials that may be disturbed.
- Noise: Construction requirements addressing local work hours, noise limits and equipment operation.
These provisions are project-specific, but they underscore a broader delivery principle: environmental controls need to be coordinated with construction sequencing, site conditions and contract specifications—not treated as an afterthought once physical work begins.
Planning implications for utilities and integrators
The Olympic and Arcadia project highlights several considerations relevant to water infrastructure teams. First, supply expansion depends on matching production, conveyance and treatment capacity. A new well or plant process cannot deliver its intended role in isolation from the pipelines and facilities that connect it to the rest of the system.
Second, upgrades at an operating treatment plant require careful integration of new equipment and additional flows with existing infrastructure. The project establishes the intended capacity change and process scope, while detailed engineering and implementation determine how those components are delivered within the site.
Finally, long-term supply goals and construction constraints must be considered together. Environmental review, mitigation requirements and coordination across the project’s locations form part of the execution framework alongside the physical infrastructure.
Conclusion
Santa Monica’s water treatment plant expansion combines restored groundwater production, a dedicated transmission pipeline and added treatment processes at the Arcadia WTP. Its practical lesson is that increasing local water capacity requires an integrated plan for wells, conveyance, treatment and construction safeguards. For utilities and project teams, aligning those elements early is central to delivering a coordinated water supply system.